The Yellow Line is a metro line on the Namma Metro rail system in Bengaluru, Karnataka, India. It is also known as the Rashtreeya Vidyalaya Road–Bommasandra Line and is referred to in Kannada as ಹಳದಿ ಮಾರ್ಗ (Haḷadi mārga). As of 2025, the line spans 19.15 km (11.90 mi), connecting Rashtreeya Vidyalaya Road with Delta Electronics Bommasandra, and is fully elevated with 16 stations.

Overview

The Yellow Line passes through the neighbourhoods of South Bengaluru, including Jayanagar, Ragigudda, BTM Layout, and Central Silk Board. It runs parallel to Hosur Road, passing through Bommanahalli, Hongasandra, Electronic City, and Bommasandra. The line interchanges with the Green Line at Rashtreeya Vidyalaya Road, and has two upcoming interchanges with the Pink Line at Jayadeva Hospital and the Blue Line at Central Silk Board. The line is owned and operated by the Bangalore Metro Rail Corporation Limited (BMRCL).

History

In the late 2000s and early 2010s, traffic on the Outer Ring Road in Bangalore increased significantly, and there was a lack of connectivity from the northern suburbs to the southeastern industrial zones. In 2009, BMRCL planned to build a line in the southern end of the city to connect it to the industrial areas of Bommasandra and Electronic City. In 2012, BMRCL submitted Phase 2 of Namma Metro, which included a 72.095 km (44.798 mi) metro expansion and the construction of two new lines — from Bannerghatta Road to Nagawara and from RV Road to Bommasandra. These were later named the Yellow Line and Pink Line. The project received approval from the Central Government of India in January 2014.

The foundation for the line was laid by Prime Minister Narendra Modi on June 14, 2016. Civil works began in November 2017.

The Yellow Line was officially inaugurated on 10 August 2025 by Prime Minister Narendra Modi and opened for public use on the following day, 11 August 2025, initially operating at a frequency of 25 minutes.

Technical Details

  • Line length: 19.15 km (11.90 mi)
  • Number of tracks: 2
  • Character: Fully elevated
  • Track gauge: 1,435 mm (4 ft 8½ in) standard gauge
  • Electrification: 750 V DC third rail
  • Signalling: Communications-Based Train Control (CBTC) signalling system
  • Rolling stock: Driverless trains manufactured by CRRC Nanjing Puzhen, assembled by Titagarh Rail Systems Limited (TRSL)
  • Depot: Hebbagodi

Stations

There are 16 stations on the Yellow Line, all of which are elevated. Four stations — Ragigudda, Jayadeva Hospital, BTM Layout, and Central Silk Board — are built alongside the Ragigudda–Silk Board flyover as a combined rail-and-road flyover structure.

# Station Name Opening Date Connections
1 Rashtreeya Vidyalaya Road 11 August 2025 Green Line
2 Ragigudda 11 August 2025 —
3 Jayadeva Hospital 11 August 2025 Pink Line (under construction)
4 BTM Layout 11 August 2025 —
5 Central Silk Board 11 August 2025 Blue Line (under construction)
6 Bommanahalli 11 August 2025 —
7 Hongasandra 11 August 2025 —
8 Kudlu Gate 11 August 2025 —
9 Singasandra 11 August 2025 —
10 Hosa Road 11 August 2025 —
11 Beratena Agrahara 11 August 2025 —
12 Electronic City 11 August 2025 —
13 Infosys Foundation Konappana Agrahara 11 August 2025 —
14 Huskur Road 11 August 2025 —
15 Biocon Hebbagodi 11 August 2025 —
16 Delta Electronics Bommasandra 11 August 2025 —

Corporate Naming

Several stations on the Yellow Line have corporate naming rights. Infosys Foundation contributed ₹115 crore (US$12 million) for the construction and maintenance of the Konappana Agrahara station, which was renamed "Infosys Foundation Konappana Agrahara" for 30 years. Biocon contributed ₹100 crore (US$10 million) towards the Biocon Hebbagodi station. In December 2024, Delta Electronics signed an agreement to provide ₹55 crore (US$5.7 million) for the Bommasandra station, which was renamed "Delta Electronics Bommasandra" for 30 years.

Funding

For Phase 2 of Namma Metro, the Central and State Governments fund approximately ₹15,000 crore. The State Government bears 30% and the Central Government bears 20% of the project cost, with the remainder obtained through senior term loans.

Delays

The line was initially scheduled to open in December 2022. Due to construction delays and late delivery of rolling stock, the opening was repeatedly postponed — to June 2023, April 2024, July 2024, and December 2024 — before finally opening in August 2025.