The UNK proton accelerator (Russian: УНК, an acronym for "Ускорительно-Накопительный Комплекс" — Accelerating and Storage Complex) is an uncompleted project of a 3 TeV large superconductor-based particle accelerator located in Protvino, near Moscow, Russia, at the Institute for High Energy Physics (IHEP).
Design and Purpose
The UNK was designed as a proton-proton collider with a center-of-mass energy of up to 3 TeV. It was to consist of two rings housed in a single underground tunnel: a first-stage conventional magnet ring accelerating protons to 400 GeV, and a second-stage superconducting ring reaching 3 TeV. The existing U-70 synchrotron (commissioned in 1967, with a final energy of 70 GeV) was intended to serve as the injector for the UNK complex. The facility was designed to support both collider and fixed-target experiments.
Construction History
Construction began in 1983. Over the course of eleven years, a 21-kilometer-long, 5-meter-wide underground tunnel was completed, along with a 2.7-kilometer connecting tunnel linking the U-70 synchrotron to the UNK. Electromagnetic, vacuum, and surveillance equipment was installed in portions of the tunnel. Progress on the project was reported as late as 1996.
Cancellation
Following the dissolution of the Soviet Union and the subsequent economic difficulties in Russia, government funding for the UNK project was halted. The project was never completed, and many of the scientists and engineers involved subsequently joined similar large-scale accelerator projects elsewhere in the world, including CERN. With the commissioning of the Large Hadron Collider (LHC) at CERN, which achieved higher energies, the Russian government redirected its particle physics funding to another domestic accelerator project — the NICA (Nuclotron-based Ion Collider fAcility) at the Joint Institute for Nuclear Research in Dubna.
Current Status
The completed tunnel infrastructure remains in place. In recent years, there have been reports of renewed interest in assessing the condition of the unfinished facility, including a 2023 allocation of 176 million rubles (approximately $25 million) by the Kurchatov Institute for High Energy Physics to evaluate the current state of the UNK complex, as part of broader efforts to strengthen Russia's capabilities in high-energy physics. However, no active construction toward completion of the original accelerator has been announced.