Tsing Lung Bridge

Tsing Lung Bridge (Chinese: 青龍大橋) is a proposed suspension bridge in Hong Kong planned to connect North Lantau with Tsing Lung Tau in the western New Territories, between Tsuen Wan and Tuen Mun. The bridge is a major component of Route 11, a strategic corridor linking the Northwest New Territories with North Lantau.

History

The Tsing Lung Bridge was originally conceived in the early 2000s as part of the Route 10 North Lantau to Yuen Long Highway. At the time of its announcement in 2002, the proposed design featured a main span of 1,418 metres (4,652 ft), making it the world's fourth-longest suspension bridge at that time — 41 metres longer than the existing Tsing Ma Bridge. Construction was initially scheduled to commence in 2003 with completion targeted for 2008, but the project was subsequently placed on hold and was not constructed.

Current Proposal

The project has since been revived and incorporated into Route 11. In June 2025, the Hong Kong Highways Department announced it would prioritise the Tsing Lung Bridge section, aiming to enhance transport connectivity between the Northern Metropolis and the Victoria Harbour (Harbour) Metropolis, aligned with the government's economic strategy of "finance in the south, innovation and technology in the north."

Design and Specifications

According to the Highways Department, the Tsing Lung Bridge will be Hong Kong's first dual four-lane sea-crossing bridge, with a main span of approximately 1.3 kilometres. It will span the Ha Pang Fairway and connect the Tsing Lung Tau Interchange and the North Lantau Interchange.

The bridge features a distinctive design with two towers of unequal height. Due to flight path restrictions for Chek Lap Kok Airport, the North Lantau tower will be approximately 55 metres lower than the tower on the Tsing Lung Tau side, resulting in an asymmetric main span. The design incorporates an "H"-shaped tower and "K"-shaped cross-beams that together symbolise "HK" for Hong Kong. The bridge requires a navigation clearance height of 57 metres — equivalent to about 20 storeys — to ensure safe passage for vessels through the confluence of Ma Wan Channel, Ha Pang Channel, and Kap Shui Mun Channel.

The bridge is designed with typhoon and earthquake resistance capabilities. The project will incorporate Digital Twin technology using sensors and artificial intelligence for real-time bridge monitoring to enhance maintenance efficiency.

Project Status

On 30 June 2026, the Highways Department signed a design and construction consultancy agreement with the Arup–Mott MacDonald Joint Venture, which also comprises China Railway Major Bridge Reconnaissance & Design Institute Co. Ltd. and other specialists. The government has stated its intention to initiate tendering in 2026, submit funding requests to the Legislative Council in 2027, and aim for completion and opening of the bridge by 2033 at the latest.

The government has also indicated plans to explore a "bridge tourism" concept, potentially opening up the bridge deck or underside and providing tourism facilities, with the aim of making the structure a new Hong Kong landmark.

Function

The Tsing Lung Bridge is intended to divert traffic from the Tuen Mun Road (Sham Tseng section) and the Ting Kau Bridge, thereby alleviating traffic congestion and enhancing the resilience of Hong Kong's overall road network. It forms part of Route 11, whose 12-kilometre main route extends from Lam Tei to North Lantau via So Kwun Wat, Tai Lam Chung, and Tsing Lung Tau, connecting with the Lantau Link and the planned Tsing Yi–Lantau Link.