The South Caucasus Pipeline (SCP), also known as the Baku–Tbilisi–Erzurum (BTE) Pipeline, is a natural gas pipeline running from the Shah Deniz gas field in the Azerbaijani sector of the Caspian Sea to Turkey, passing through Georgia. It runs broadly parallel to the Baku–Tbilisi–Ceyhan (BTC) crude oil pipeline.
Overview
- Status: Operational
- Type: Natural gas
- Operator: BP (on behalf of the Shah Deniz Consortium)
- Commissioned: 2006 (Phase 1); 2018 (SCP Expansion / Phase 2)
- Length: Approximately 692 kilometers (430 miles)
- Diameter: 42 inches (1,067 mm) for the expansion sections; 28 inches (711 mm) for the original section in Georgia (looped by the expansion).
- Capacity: Initial capacity ~7 billion cubic meters per year (bcm/y); Expanded capacity ~23 bcm/y (total ~30 bcm/y).
Route
The pipeline originates at the Sangachal Terminal near Baku, Azerbaijan. It crosses Azerbaijan to the Georgian border, traverses Georgia (passing near Tbilisi and through the Trialeti Range via the Akhaltsikhe region), and crosses the Georgian–Turkish border near Vale/Posof. It terminates at the Erzurum gas hub in eastern Turkey, where it connects to the Turkish national gas grid and the Trans-Anatolian Natural Gas Pipeline (TANAP).
History and Development
- Intergovernmental Agreements: Signed in 2001 (Azerbaijan–Georgia) and 2002 (Georgia–Turkey).
- Construction (Phase 1): Began in 2004; inaugurated in 2006; commercial gas flows to Turkey started in 2007.
- SCP Expansion (SCPX): Initiated to transport gas from Shah Deniz Stage 2. Construction began in 2015. The expansion involved laying a new 48-inch (later executed as 42-inch) diameter pipeline looped alongside the existing line in Georgia and a new line in Azerbaijan. First gas from the expansion reached Turkey in June 2018.
- Southern Gas Corridor: The SCP constitutes the central segment of the Southern Gas Corridor, linking the Caspian basin to European markets via the Trans-Anatolian Pipeline (TANAP) and the Trans-Adriatic Pipeline (TAP).
Technical Specifications
- Compressor Stations: The system includes compressor stations in Azerbaijan (Azizbeyov, Siyazan) and Georgia (Kakheti, Tianeti, Akhaltsikhe) to maintain pressure.
- Design Pressure: Up to 95 bar (standard) / higher for expansion segments.
- Metrology: Metering stations are located at the Sangachal Terminal (entry), the Georgia–Turkey border (Vale), and the terminus at Erzurum.
Commercial Structure
The pipeline is owned by the South Caucasus Pipeline Company (SCPC), a consortium whose shareholders mirror the Shah Deniz field partners (historically including BP, SOCAR, TPAO, LUKOIL, NICO, SGC, and others). BP acts as the technical operator. Capacity is booked by Shah Deniz producers and shipped under long-term gas sales agreements.
Geopolitical and Economic Significance
The SCP is a critical infrastructure asset for the diversification of European energy supplies, reducing dependence on Russian gas. It provides the primary export route for Azerbaijani gas to Turkey and onward to Greece, Bulgaria, Italy, and Southeast Europe via TANAP and TAP. It generates significant transit revenue for Georgia and Azerbaijan.