Rajasthan Atomic Power Station

Rajasthan Atomic Power Station (RAPS), also known as Rawatbhata Atomic Power Station, is a nuclear power plant located at Rawatbhata in the Chittorgarh district of Rajasthan, India. It is owned and operated by the Nuclear Power Corporation of India Limited (NPCIL). The station is one of India's major nuclear power generation facilities and utilizes Pressurized Heavy Water Reactor (PHWR) technology.

History and Development Construction of the first unit began in the 1960s with Canadian collaboration under the Colombo Plan, following an agreement between India and Canada. The first unit (RAPS-1) achieved criticality in 1972 and began commercial operation in 1973. It was the first PHWR to be commissioned in India. Following India's nuclear test in 1974, Canadian support was withdrawn, leading India to indigenize the technology for subsequent units.

Reactor Units As of the current operational status, the station comprises eight units:

  • RAPS-1: 100 MWe (PHWR), commissioned December 1973. Placed under IAEA safeguards in 2010. Currently under extended shutdown for life extension assessment/en-masse coolant channel replacement (EMCCR).
  • RAPS-2: 200 MWe (PHWR), commissioned April 1981. Placed under IAEA safeguards in 2010. Underwent EMCCR and life extension; returned to service.
  • RAPS-3: 220 MWe (PHWR), commissioned June 2000. Indigenous design.
  • RAPS-4: 220 MWe (PHWR), commissioned December 2000. Indigenous design.
  • RAPS-5: 220 MWe (PHWR), commissioned February 2010. Indigenous design.
  • RAPS-6: 220 MWe (PHWR), commissioned March 2010. Indigenous design.
  • RAPS-7: 700 MWe (PHWR), first criticality achieved September 2024. First of the indigenous 700 MWe fleet.
  • RAPS-8: 700 MWe (PHWR), under construction/commissioning phase (first criticality anticipated following Unit 7).

Technical Specifications

  • Reactor Type: Pressurized Heavy Water Reactor (PHWR).
  • Fuel: Natural Uranium Dioxide (UO2) for 220 MWe units; Slightly Enriched Uranium (SEU) or MOX fuel planned/used for 700 MWe units to optimize burnup.
  • Moderator/Coolant: Heavy Water (D2O).
  • Containment: Double containment for 220 MWe units; Passive Decay Heat Removal System and steel-lined containment for 700 MWe units.

Safeguards and International Status Units 1 and 2 were placed under International Atomic Energy Agency (IAEA) safeguards in 2010 as part of India's separation plan under the Indo-US Civil Nuclear Agreement. Units 3 through 6 are not under IAEA safeguards. Units 7 and 8 have been declared for IAEA safeguards.

Capacity and Generation The total installed capacity of the operational units (1 through 6) is approximately 1,180 MWe. With the commercial operation of Units 7 and 8 (700 MWe each), the total planned capacity will reach approximately 2,580 MWe, making it one of the largest nuclear power complexes in India.

Safety and Incidents

  • 1993 Incident: A significant heavy water leak occurred at RAPS-1, leading to a prolonged shutdown. The unit was later restarted after repairs.
  • 2012 Incident: A leak in the moderator system of RAPS-5 led to an automatic shutdown. The unit was returned to service after repair.
  • The station operates under the regulatory oversight of the Atomic Energy Regulatory Board (AERB) of India. Safety upgrades, including post-Fukushima stress tests, have been implemented across units.
Browse

More topics to explore

    Browse all articles