The North Blyth Biomass Project was a proposed biomass-fired power station planned to be located at North Blyth, Northumberland, on the north bank of the River Blyth near its tidal estuary. If commissioned, it would have had a generating capacity of 100 megawatts (MW), enough electricity to provide for approximately 170,000 homes.
Development
In September 2008, the Port of Blyth authority announced that it was planning to build a biomass power station on the redundant Bates Colliery site to the north of Blyth. In May 2009, the Port of Blyth selected the renewable energy company Renewable Energy Systems (RES) as the developer for the power station.
In December 2009, RES and the Port of Blyth decided to relocate the proposed station site to the north bank of the estuary at North Blyth, near the port's new bulk materials handling facility. The stated reason for the move was to reduce the number of road movements supplying the station and to give the station access to rail facilities.
In September 2010, RES released the first promotional images of the proposed station to the public during a series of exhibitions at Blyth Community Enterprise Centre, the North Blyth Club, and Cambois Welfare Institute. The company reported that approximately 75% of attending local residents expressed enthusiasm for the project, attributed largely to expected local employment creation, area regeneration, and contributions to renewable energy development in the region.
If constructed, the project was expected to create between 200 and 300 full-time jobs at the peak of construction and approximately 40 permanent jobs once operational. Planning permission was expected to be submitted to the Infrastructure Planning Commission in early 2011; the estimated build time was around 30 months.
Proposed specification
The station would have generated 100 MW of electricity, equating to over 750 million kilowatt-hours per year. It would have burned between 500,000 and 900,000 tonnes of biomass fuels annually, including woodchips, wood pellets, wood briquettes, and recycled chipped wood, delivered via the nearby port. The project was projected to reduce carbon dioxide emissions by over 300,000 tonnes per year.
Consent and cancellation
Renewable Energy Systems was granted government consent on 24 July 2013 to build the approximately £250 million project. The Secretary of State issued a Development Consent Order treating the scheme as a nationally significant infrastructure project under the Planning Act 2008 (as set out in The North Blyth Biomass Power Station Order 2013).
However, the project was cancelled on 6 March 2014, when RES withdrew from the development. The suspension was attributed to the withdrawal of a key investment partner from the project.
References
- Wikipedia: "North Blyth Biomass Project"
- The North Blyth Biomass Power Station Order 2013, legislation.gov.uk