The Lanco Amarkantak Power Plant is a coal-fired thermal power station located in Pathadi village, Korba district, in the state of Chhattisgarh, India. It is owned and operated by Lanco Amarkantak Power Limited, a subsidiary of Lanco Infratech Limited.
Capacity and Units The plant has a total installed capacity of 1,920 MW, developed in two phases:
- Phase I: 2 × 300 MW (Units 1 & 2), commissioned in 2009–2010.
- Phase II: 2 × 660 MW (Units 3 & 4), commissioned in 2015–2016.
Fuel and Logistics The plant utilizes coal as its primary fuel. Coal supply is sourced primarily from the captive coal blocks allocated to the company (such as the Gondkhari coal block) and through linkages from Coal India Limited subsidiaries, notably South Eastern Coalfields Limited (SECL). Water for the plant is drawn from the Hasdeo River.
Technology
- Phase I units utilize sub-critical boiler technology.
- Phase II units utilize supercritical boiler technology, offering higher efficiency and lower specific coal consumption compared to sub-critical units.
Status and Ownership Developments Lanco Infratech Limited, the parent group, underwent corporate insolvency resolution proceedings under the Insolvency and Bankruptcy Code (IBC) starting in 2017. Consequently, the ownership and control of Lanco Amarkantak Power Limited have been subject to resolution processes. As of recent developments, the plant's ownership has transitioned following the approval of resolution plans by the National Company Law Tribunal (NCLT), with entities such as the Power Finance Corporation (PFC) and Rural Electrification Corporation (REC) acquiring significant stakes or control through the resolution process.
Significance The plant is a significant contributor to the power grid of Chhattisgarh and the Western Region grid, supplying electricity to multiple states through long-term Power Purchase Agreements (PPAs) and merchant sales.