Koldam Dam, officially known as the Koldam Hydropower Station, is an embankment dam (rock-fill with clay core) on the Sutlej River in Himachal Pradesh, India. It is located in Salaper, straddling the border between Bilaspur district and Mandi district, approximately 18 km from Bilaspur off the Chandigarh-Manali Highway (NH-21) near Barmana.
Overview
The dam is owned and operated by NTPC Limited (formerly National Thermal Power Corporation Limited). Its primary purpose is hydroelectric power generation, supporting an installed capacity of 800 MW. The dam stands 167 m (548 ft) tall from its foundation, with a crest length of 474 m (1,555 ft) and a crest width of 14 m (46 ft). The dam volume is approximately 12,000,000 m³. The reservoir has a total capacity of 576,000,000 m³ and a surface area of 12.5 km², extending up to 40 km in length.
History
The Koldam project was first conceived in the mid-1960s, with investigations at various possible sites ongoing since 1966. An initial project report prepared by 1975 proposed a rock-fill dam with an installed capacity of 600 MW. The Himachal Pradesh State Electricity Board (HPSEB) took over investigation and studies in October 1984, and the project capacity was revised to 800 MW, though work did not commence due to lack of funds.
NTPC took over the project in 2000, and the project report was revised to include a 167 m high rock-fill dam with a surface power house at the dam's toe, with an installed capacity of 4 × 200 MW. The foundation stone was laid on 5 June 2000 by Prime Minister Atal Bihari Vajpayee, and main construction began on 14 January 2004.
Construction
The dam construction contract was awarded to Thailand's ITD Public Company Limited. A joint venture of BHEL, Toshiba, and Marubeni supplied the turbines and generators.
The project experienced significant delays due to geological issues and the declaration of part of the reservoir area in 2006 as an extension of the Majathal Wildlife Sanctuary. Attempts to impound the reservoir failed multiple times between December 2013 and April 2014 due to problems with sealing the diversion tunnels. Successful impounding was eventually achieved between November 2014 and January 2015.
Power Generation
The power station contains four 200 MW Francis-type turbines, for a total installed capacity of 800 MW. The units were commissioned as follows:
| Unit | Capacity | Commissioning Date |
|---|---|---|
| 1 | 200 MW | 31 March 2015 |
| 2 | 200 MW | 30 March 2015 |
| 3 | 200 MW | 10 April 2015 |
| 4 | 200 MW | 12 June 2015 |
The annual generation is approximately 3,055 GWh (3,055 million units), with a capacity factor of 43.58%. The static hydraulic head is 131.2 m (430 ft).
Spillway
The dam features a chute-type spillway with a flip bucket and six radial gates, each 17.1 m wide and 17.74 m tall. The spillway has a discharge capacity of 16,500 m³/s (582,692 cu ft/s).