Jagdbergtunnel is a twin-tube road tunnel on the Bundesautobahn 4 (A4) in the Free State of Thuringia, Germany, located west of the city of Jena between the Magdala and Jena-Göschwitz junctions. With a length of approximately 3,074 metres (north tube) and 3,070 metres (south tube), it is one of the ten longest road tunnels in Germany. It is named after the 288-metre-high Jagdberg, which rises between Jena-Göschwitz and the tunnel's eastern portal.
Purpose and context
The tunnel forms the core of the so-called Leutratal bypass, an 11.8-kilometre, six-lane section of the A4 built under the German Unity Transport Project No. 15 (Verkehrsprojekt Deutsche Einheit Nr. 15). It replaced an older four-lane route through the Leutratal valley that had steep gradients, narrow curve radii, largely absent hard shoulders, and a comparatively high accident rate. The Leutratal is an ecologically sensitive area containing a nature reserve noted for a large number of orchid species, together with a designated FFH (Habitats Directive) site and an EU bird protection area. Relocating the road into a tunnel made it possible to expand capacity while removing traffic from the valley; the old route was subsequently dismantled and the land renaturalised.
Technical data
- Construction method: drill-and-blast excavation (Sprengvortrieb) with sprayed-concrete (shotcrete) outer lining and a reinforced-concrete inner lining
- Cross-section: two separate tubes, each with three lanes (3.50 m wide) and 1 m emergency walkways on both sides
- Gradient: approximately 2.9–2.95 percent, rising toward the west
- Maximum rock cover: about 134 m
- Safety infrastructure: emergency lay-bys at intervals of roughly 560 m and ten cross-passages equipped with fire doors at intervals of about 280 m
- Ventilation: longitudinal ventilation by jet fans, supplemented by a central exhaust shaft approximately 130–140 m high located near the midpoint of the tunnel
- Traffic management: variable-message gantries, speed enforcement, distance measurement at both portals, and continuous video surveillance
- Geology: the tunnel passes through Lower Muschelkalk and various divisions of the Röt, crossing a fault system known as the Leutrastörung
Fire protection
The Jagdbergtunnel was the first motorway tunnel in Germany to be equipped not only with fire detection but also with an automatic fire-fighting system. A compressed-air foam extinguishing installation covers both tubes and is designed to detect, localise, and combat a fire automatically in 75-metre sections. This measure was adopted in part so that vehicles carrying dangerous goods would not have to be diverted over long detours around the tunnel — a practice that had applied at Germany's longest road tunnel, the Rennsteigtunnel. The system demonstrated its effectiveness during a truck fire in July 2016 and a car fire in August 2017, allowing traffic to be restored after approximately 15 and 30 minutes respectively and limiting structural damage.
Construction and opening
Excavation began on 25 September 2008 with a ceremonial first blast in the south tube. Breakthrough in the south tube occurred on 27 August 2009 (some sources give 18 August 2009), ahead of schedule, followed by the north tube in early September 2009. Both tubes were driven simultaneously from the west and east portals. Construction was carried out on behalf of the Federal Republic of Germany, with planning and project execution assigned by the Free State of Thuringia to DEGES (Deutsche Einheit Fernstraßenplanungs- und -bau GmbH). The tunnel was opened to traffic toward the west (Eisenach/Frankfurt direction) on 30 October 2014 and toward the east (Görlitz/Dresden direction) on 18 November 2014, following a three-month test phase for emergency services.
Costs
The approved construction costs were stated as approximately 385 million euros, against an estimate of 295 million euros in 2008. Cost increases were attributed to additional safety installations, including the automatic fire-fighting system (reported at roughly 14 million euros extra) and to remedial works for water ingress, which required subsequent installation of sealing structures and drainage at a reported additional cost of four to five million euros, and which delayed completion by about one year. Some sources cite a lower figure (around 210 million euros) for the structural works alone.
Traffic
Daily traffic volumes on the section are forecast at up to 67,000 vehicles, with a projected rise to 80,000 vehicles, about a quarter of which would be heavy goods vehicles.
Sources
- Wikipedia (German and English articles on Jagdbergtunnel)
- Structurae: Jagdbergtunnel (Bucha, 2014)
- DAUB (Deutscher Ausschuss für unterirdisches Bauen): project database entry "Jagdbergtunnel – BAB A4"
- Thüringer Allgemeine, report on the tunnel opening, 30 October 2014