The Huntington Beach Desalination Plant is a proposed seawater desalination facility in Huntington Beach, California, that was put forward by Poseidon Resources Corporation (operating as Poseidon Water). The project was designed to produce approximately 50 million US gallons (190 megaliters) of potable drinking water per day using reverse osmosis technology. The proposed site was located adjacent to the AES Huntington Beach Power Station, within Orange County, California.
Project Overview
The facility was intended to provide water for approximately 2.5 million residents in northern and central Orange County. At the time of the proposal, the region obtained roughly 77 percent of its water supply from local groundwater and the Santa Ana River, with the remainder imported from outside sources. The Orange County Water District signed a nonbinding term sheet to purchase the plant's output to reduce reliance on treated imported supplies from the Metropolitan Water District of Southern California. However, some local water agencies, such as the Irvine Ranch Water District, declined to participate, citing the availability of less expensive alternative water sources.
Poseidon Water planned to lease the approximately 11-acre (4.5-hectare) site from AES Corporation. The project intended to reuse ocean water intake infrastructure from the 1950s-era power plant, which was being rebuilt to use air rather than seawater for cooling. The plant design included a brine diffuser system intended to disperse concentrated seawater back into the ocean.
Regulatory History
Poseidon Water began seeking a site in Orange County in 1999. The City of Huntington Beach certified an Environmental Impact Report (EIR) in 2005 and granted a conditional use permit and coastal development permit in 2006. After Poseidon submitted a modified application, the city prepared and certified a Subsequent EIR in 2010.
In 2015, the State Water Resources Control Board adopted new seawater desalination regulations. Poseidon subsequently sought to amend its intake lease arrangements with the State Lands Commission. In April 2021, the Santa Ana Regional Water Quality Control Board approved a permit for the project, which required certain environmental mitigations.
In May 2022, the California Coastal Commission voted unanimously to deny the project's Coastal Development Permit. The decision followed a staff report that recommended denial. Concerns cited by commissioners included the potential for increased water rates affecting disadvantaged households, significant impacts on marine life from the proposed intake system, and the cost-effectiveness of the project relative to alternatives. The Coastal Commission staff had recommended an offshore subsurface intake to reduce harm to fish eggs and larvae, a design alternative rejected by the company due to cost. Following the denial, Poseidon Water abandoned the project.
Project Cost and Stated Scale
The project was reported to have a projected cost of approximately $1.4 billion. If completed, it would have been capable of producing roughly 56,000 acre-feet of fresh water per year. The plant would have been the second major seawater desalination facility associated with Poseidon Water in California, following the Carlsbad Desalination Plant, which began operations in San Diego County in 2015.
Post-Denial Status
As of the available reporting, the Huntington Beach Desalination Plant has not been constructed. The Coastal Commission's unanimous denial in May 2022 effectively ended the project as proposed, and Poseidon Water decided not to pursue the development further at that location. The decision has been noted as influential in establishing regulatory precedent for seawater desalination project evaluations in California.