The Hovenring is a suspended cycle path roundabout in the province of North Brabant in the Netherlands. It is situated between the localities of Eindhoven, Veldhoven, and Meerhoven, which accounts for its name, and is the first of its kind in the world.
History
The Hovenring was first conceived in 2008, when increased traffic between Eindhoven and Veldhoven began to overwhelm the capacity of the roundabout at the crossing of the Heerbaan and Meerenakkerweg (Heistraat). To improve traffic flow and safety, it was decided to completely separate motorized and bicycle traffic. The city council of Eindhoven decided to develop an eye-catching project, in keeping with the ambitions of the Brainport top technology region.
The design for the Hovenring was made by the ipv Delft design agency. The name was chosen through a competition held among the population of Eindhoven and Veldhoven. Literally, the name means "ring of the Hovens," referring to Eindhoven, Veldhoven, and Meerhoven. The name also alludes to the suspended ring structure, the central pylon (the "needle"), and the lights that adorn the construction, referencing Eindhoven's unofficial designation as the "city of lights."
Construction started on 11 February 2011. The new crossing was opened on 30 December 2011, but was closed about a week later when the suspension cables were found to vibrate in a manner considered harmful. The Hovenring was finally opened to the public on 29 June 2012.
Design and Construction
The Hovenring is officially a roundabout, but is in fact a circular cable-stayed bridge. The deck has a diameter of 72 metres (236 ft) and is suspended from a single 70-metre (230 ft) tall central pylon by 24 cables. The entire construction is made of steel.
Vibration Issues
The bridge had to be closed shortly after its initial delivery due to unexpected wind-induced vibrations in the cables. An investigation was undertaken by professors of civil and mechanical engineering from Eindhoven University of Technology, Delft University of Technology, and Professor Alberto Zasso of the Politecnico di Milano. The problem was identified as vortices of wind forming in the lee of the cables, causing heavier vibrations than anticipated during design. The solution involved applying additional dampers to the cables, though an initial incorrect mounting of the dampers caused an additional delay of one month.
Predecessors and Comparisons
A notable predecessor is the cycle overpass roundabout of Tjensvollkrysset in Stavanger, Norway, which opened in 2010 and shares a similar 72-metre diameter, though it is constructed of concrete rather than steel. Comparisons have also been made with the 2011 circular pedestrian overpass in Lujiazui, Pudong, Shanghai, and a similar overpass from 2012 in Rzeszów, Poland.