The Gosfield Wind Project is a wind power facility located in the municipality of Kingsville, Essex County, Ontario, Canada. It is one of the early utility-scale wind farms developed in the province.
Location and Geography The project is situated on the north shore of Lake Erie, an area characterized by favorable wind resources due to lake-effect dynamics. The site spans agricultural land leased from local landowners.
Technical Specifications
- Capacity: The facility has a total installed capacity of 50.6 megawatts (MW).
- Turbines: It consists of 22 Siemens SWT-2.3-101 wind turbines, each with a nameplate capacity of 2.3 MW.
- Commissioning: Commercial operations commenced in October 2010.
Development and Ownership The project was originally developed by AIM PowerGen Corporation. Following the acquisition of AIM PowerGen by Brookfield Renewable Power (now Brookfield Renewable Partners) in 2010, the asset became part of Brookfield's North American renewable energy portfolio. Brookfield Renewable operates the facility.
Regulatory and Contractual Framework The Gosfield Wind Project operates under a 20-year Power Purchase Agreement (PPA) with the Ontario Power Authority (subsequently the Independent Electricity System Operator, IESO) under the province's Feed-in Tariff (FIT) program / Renewable Energy Standard Offer Program (RESOP) legacy frameworks. The project received its Renewable Energy Approval (REA) from the Ontario Ministry of the Environment in accordance with the Green Energy and Green Economy Act, 2009.
Grid Connection The generated electricity is transmitted via a substation and a 115 kV transmission line connecting to the Hydro One Networks Inc. grid at the Keith Transformer Station.
Environmental and Community Aspects As part of the approval process, environmental assessments were conducted addressing avian and bat mortality, noise levels, and shadow flicker. The project includes a community liaison committee and provides municipal tax revenue to the Town of Kingsville.