Chuitna Coal Project

The Chuitna Coal Project was a proposed surface coal mine and associated infrastructure development located in the Beluga Coal Fields of south-central Alaska, approximately 45 miles (72 km) west of Anchorage. The project was primarily developed by PacRim Coal LP, a subsidiary of the Texas-based company PacRim Coal.

Project Scope and Design The proposed mine targeted the Chuitna River watershed, specifically the Upper Chuitna Creek and Middle Creek basins. The project design called for a conventional open-pit (strip) mining operation utilizing draglines, trucks, and shovels to extract sub-bituminous coal from the Tertiary-aged Tyonek Formation. The initial plan envisioned a mine life of approximately 25 years, with an estimated recoverable reserve of roughly 300 million tons of coal. The planned production rate was up to 12 million tons per year.

Infrastructure plans included:

  • A mine site covering approximately 8,000 acres (3,237 hectares).
  • A 12-mile (19 km) overland conveyor system to transport coal from the pit to a port facility.
  • A deep-water marine terminal at Ladd Landing on the west side of Cook Inlet for loading bulk carriers.
  • A 35-megawatt coal-fired power plant to supply electricity to the mine and camp facilities.
  • Worker housing and support facilities.

Regulatory and Permitting History The project underwent an extensive federal and state permitting process spanning over two decades. Key milestones included:

  • Environmental Impact Statement (EIS): The U.S. Army Corps of Engineers (USACE) served as the lead federal agency for the National Environmental Policy Act (NEPA) process. A Draft EIS was published in 2007, and a Final EIS was released in 2016.
  • Clean Water Act Section 404 Permit: The project required a permit from the USACE for the discharge of dredged or fill material into waters of the United States, specifically regarding the proposed mining through and reconstruction of approximately 13.7 miles (22 km) of salmon-bearing streams (Middle Creek and Upper Chuitna Creek). This "mine-through" methodology—removing the streams to access coal seams and reconstructing them post-mining—was a central point of regulatory scrutiny and public controversy.
  • State Permits: The Alaska Department of Natural Resources (DNR) issued a Reclamation Plan Approval and a Right-of-Way lease. The Alaska Department of Environmental Conservation (DEC) issued waste management and air quality permits.

Environmental and Social Concerns The project faced significant opposition from a coalition of environmental organizations (including Cook Inletkeeper, the Sierra Club, and the Alaska Center for the Environment), commercial and sport fishing groups, and some Alaska Native entities (including the Tyonek Native Corporation and the Village of Tyonek). Primary concerns cited in the EIS and public comments included:

  • Fisheries Impact: Potential degradation of habitat for all five species of Pacific salmon (Chinook, Coho, Sockeye, Pink, Chum) in the Chuitna River watershed, which supports commercial, sport, and subsistence fisheries.
  • Water Quality: Risks of sedimentation, altered hydrology, and potential leaching of pollutants (such as mercury and selenium) into Cook Inlet.
  • Stream Reconstruction Uncertainty: Scientific debate regarding the feasibility and ecological equivalency of reconstructing complex, functioning salmon streams after complete removal of the original channel and floodplain.
  • Cultural Resources: Impacts on traditional use areas and cultural sites of the Dena'ina Athabascan people of Tyonek.
  • Climate Change: Lifecycle greenhouse gas emissions from the combustion of the exported coal.

Project Status and Termination In March 2017, PacRim Coal LP announced the suspension of the project and submitted a request to the USACE to withdraw its Clean Water Act Section 404 permit application. The company cited "current market conditions" and the "lengthy and expensive permitting process" as reasons for the withdrawal. Consequently, the USACE terminated the EIS process.

As of the latest available public records, the project remains inactive. The state permits issued by the DNR and DEC have either expired or been relinquished. No active mining operations have ever commenced at the site.