The British Rail Mark 5 was the designation given to the planned passenger rolling stock intended for the InterCity 250 project, a proposal by British Rail to improve operating speeds on the West Coast Main Line (WCML). The project was ultimately cancelled in July 1992 before any vehicles were built.

Background and Design

The Mark 5 stock was designed to succeed the Mark 4 coaches then entering service on the East Coast Main Line (ECML). Unlike the Mark 4, whose sloping sides reflected an earlier, briefly contemplated use of tilting "Mark 4 T" stock on the WCML, the Mark 5 was designed for non-tilting operation. It was anticipated that following introduction on the WCML, the coaches might later be used in InterCity 250 builds for the East Coast and Great Western Main Lines, potentially replacing Mark 3 and Mark 4 stock used in the InterCity 125 and 225 formations.

Earlier British Rail Research studies in the early 1980s examined the feasibility of a 25.5 m (approx. 84 ft) long InterCity coach intended to succeed the Mark 3, targeting a 125 mph (201 km/h) operating speed with a 155 mph (249 km/h) capability if fitted with a hydrokinetic brake. The eventual Mark 5 specification settled on a 26 m (85 ft 4 in) length over buffers, an increase from the 23 m (75 ft) of the Mark 4, based on British Rail studies indicating such a length was feasible within the UK loading gauge and offered reduced maintenance costs.

Project Description

The InterCity 250 project intended to build 30 full trains, each comprising a Class 93 electric locomotive, nine Mark 5 passenger coaches, and a Mark 5 Driving Van Trailer operating in push-pull formation. The coaches were specified to be capable of 155 mph (249 km/h) and were required to be equivalent in weight to the shorter Mark 4 coaches, which had been considered overweight.

Specifications for the Mark 5 included an integral steel or aluminium monocoque body construction, hinged plug doors (pneumatically operated), air-conditioned and pressure-sealed interiors, disc braking, and a possible active suspension system contributing toward a desired 30% improvement in ride quality over the Mark 3 coach. Interior mock-ups, designed by FM Design and constructed at British Rail's Engineering Development Unit at the Railway Technical Centre in Derby during 1991, indicated a 2+2 seating arrangement in standard class (88 seats per coach) and 2+1 in first class (52 seats per coach).

In early 1991, tenders were called for up to 45 ten-carriage sets, with GEC Alsthom, Bombardier/Prorail, and British Rail Engineering Limited/ABB invited to bid. The project was terminated due to high costs; the Class 93 locomotives alone were estimated to cost £380 million, and funding was limited following the completion of the ECML electrification project.

Legacy

After the InterCity 250 project was cancelled, the InterCity West Coast franchise was later operated by Virgin Trains from the privatisation of British Rail until 2019, which commissioned Class 390 electric multiple units instead of the proposed Class 93 locomotive and separate Mark 5 carriage formation. Network Rail track design standards had previously used the Mark 5 coach to represent coaching stock with 19 m (62 ft) bogie centres; references to this requirement were removed from June 2016.

The "Mark 5" designation was subsequently reused for a separate family of coaches: the British Rail Mark 5 built by Spanish manufacturer CAF for Caledonian Sleeper, and the British Rail Mark 5A push-pull coaches originally built for TransPennine Express.