116th Street station (Second Avenue Subway)

The 116th Street station is a planned station along the IND Second Avenue Line of the New York City Subway, operated by the Metropolitan Transportation Authority (MTA). It would be located at the intersection of Second Avenue and 116th Street in the East Harlem neighborhood of Manhattan, New York City. Proposed since 1968, the station is expected to be built as part of Phase 2 of the Second Avenue Subway project.

Location and design

The station would be situated at East 116th Street and Second Avenue in East Harlem. Under current plans, it would be an underground station with two tracks and a single island platform, approximately 59 feet (18 m) wide. The platform would be 25 feet 3 inches (7.70 m) wide, and the height between the platform and the ceiling would be 16 feet 8 inches (5.08 m). The station would extend roughly 41 feet (12 m) deep from street level to trackbed.

Two exits are planned: one at the northeast corner of 116th Street and Second Avenue, and another at the northeast corner of 118th Street and Second Avenue. The station would include additional elevators in compliance with the Americans with Disabilities Act of 1990, with elevators planned at two entrances (compared to Phase 1 stations, which included elevators at only one entrance).

History

Background and early proposals

The Second Avenue Line was originally proposed in 1919 as part of a massive expansion of what would become the Independent Subway System (IND). Work on the line never commenced due to the Great Depression. Numerous plans for the Second Avenue Subway appeared throughout the 20th century but were generally deferred due to lack of funds. In anticipation of the never-built line, the Second and Third Avenue elevated lines were demolished in 1942 and 1955, respectively.

The MTA proposed a full-length Second Avenue Subway as part of its 1968 Program for Action. Notably, this original plan did not include a station at 116th Street; the nearest planned stops were at 106th Street and 125th Street. Construction began in 1973 on the tunnel section between 110th and 120th Streets, but work halted in September 1975 due to New York City's fiscal crisis, and the tunnels were sealed. This segment was built with three tracks, with the middle track intended for train repair and inspection.

In 1999, the Regional Plan Association recommended building a full-length Second Avenue Subway that would include 116th Street as one of its planned 31 stations, intended to serve central and southern East Harlem.

Introduction to Phase 2 plans

In March 2007, plans for the Second Avenue Subway were revived. Phase 1, which opened on January 1, 2017, extended the line's northern terminal to 96th Street. The 116th Street station was added to the plans due to community requests during Phase 1 planning in the early 2000s.

Phase 2, planned between 96th and 125th Streets, received $525 million in the MTA's 2015–2019 Capital Plan for planning and design work. In July 2018, the MTA released a supplemental environmental assessment indicating that the 116th Street station would be relocated about 30 feet (9.1 m) north compared to previous proposals, eliminating a curve at the south end of the platform. The design also revised the ancillary facilities and entrances.

Current construction plans

Because the existing 1970s tunnel had three tracks and no planned station at 116th Street, earlier proposals called for partially demolishing the existing tunnel to make room for the station. However, by April 2019, it was decided to build a platform over the center trackway instead of totally rebuilding the structure, saving a considerable amount of money.

In August 2025, the MTA board awarded a $1.97 billion contract to Connect Plus Partners, a joint venture between Halmar International and FCC Construction. This contract includes the construction of the 125th Street station shell, reconstruction of the existing tunnel near the 116th Street station, and new tunnels between Second Avenue–120th Street and Lenox Avenue–125th Street. The broader Phase 2 project carries an expected cost of approximately $7 billion.

Service

When opened, the station is expected to initially be served by the Q train, with the T train providing service when Phase 3 of the line is built. It would sit between the planned 106th Street station to the south and the Harlem–125th Street station to the north.

References

  • Wikipedia, "116th Street station (Second Avenue Subway)"
  • MTA, "Second Avenue Subway Phase 2"
  • MTA, Contract 2 documentation (2025)
  • NYC Urbanize, "New renderings for Second Avenue Subway phase two"
Browse

More topics to explore

    Browse all articles